Turn a cable count and a straight run length into kit sections, splices, sleepers, hardware weight and the grounding count. This is an estimating aid only. Quote from your distributor and confirm against the assembly drawings.

How it counts

Precomputed: bridge kits

Bridge-kit sections + splices, with total hardware weight, for one straight run (no growth allowance)
Kit24 ft48 ft80 ft120 ft200 ft
4 runs · MT-F1542-113 + 2
238 lb
6 + 5
479 lb
10 + 9
801 lb
15 + 14
1,203 lb
25 + 24
2,008 lb
8 runs · MT-F15433 + 2
356 lb
6 + 5
721 lb
10 + 9
1,208 lb
15 + 14
1,816 lb
25 + 24
3,033 lb
12 runs · MT-F15953 + 2
581 lb
6 + 5
1,181 lb
10 + 9
1,982 lb
15 + 14
2,983 lb
25 + 24
4,985 lb

Read each cell as "sections + splices", with the total hardware weight below.